Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jul 2020 Beypore Zone - Total length of pipe to be laid - 35.14km Total length of pipe laid - 33.44km (kRK laid - 25.57 km ,SEPC laid - 7.87km) Balance to be laid - 1.71km Charged length -33.43km Handed over to PH division - 33.43km No of Connections- 2700 Kozhikode Proj AE 1 Urban
01 Jul 2020 Malaparamba Zone Total length of pipe to be laid - 133.15km Total length of pipe laid - 69.52km (kRK laid - 24.10km ,SEPC laid - 45.42km) Balance to be laid- 63.63km Charged length - 6.22km Handed over to PH division - 6.22km Kozhikode Proj AE 1 Urban
01 Jul 2020 Kovoor Zone- Total length of pipe to be laid - 75.07km Total length of pipe laid - 62.08km (kRK laid - 17.75km ,SEPC laid - 44.33 ) Balance to be laid - 12.99km Charged length - 21.84km Handed over to PH division- 21.84 Kozhikode Proj AE 1 Urban
01 Jul 2020 Cheruvannur Zone- Total length of pipe to be laid - 91.92km Total length of pipe laid - 89.26km (kRK laid - 34.11km SEPC laid- 55.15km) Balance to be laid - 2.66km Charged length - 71.00km Handed over to PH division - 71.00km Kozhikode Proj AE 1 Urban
01 Jul 2020 Kadlundi panchayath Total length of pipe to be laid - 69.88km Total length of pipe laid - 68.91km KRK laid - 35.52km SEPC laid - 33.38km Charged length - 68.90km Handed over to PH division - 68.90km No of Connections - 5010 Kozhikode Proj AE 1 Urban
01 Jul 2020 Total Length of pipe to be laid - 605.30km KRK laid - 170.51km SEPC laid - 279.18km balance to be laid - 155.61km Kozhikode Proj AE 1 Urban