Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2021 | Final bill submitted to HO on 24.08.2021, As laid drawing submitted by contractor SPCL. But the same is returned for re-submitting after incorporating correction noted. | Kozhikode Project Dn AE5 | |
27 Jan 2021 | Contract terminated at the risk and cost of contractor vide order no. KWA/JICA/KKD-2557-P3R1/2012, dated 03.09.2020. On termination, the physical progress achieved was 64.21%. Final bill submitted to CE(P&O) | Kozhikode Proj AEE Urban | |
27 Nov 2020 | JICA Closure bill under preparation | Kozhikode Project Dn EE | |
13 Nov 2020 | JICA Closure bill under preparation | Kozhikode Project Dn EE | |
18 Aug 2020 | Contract terminated vide order No KWA/JICA/CE/KKD/P3R1/749/2015 of CE(P&O) dated 17/06/2020. | Kozhikode Proj AE 1 Urban | |
01 Jul 2020 | Eravathukunnu south Zone- Total length of pipe to be laid - 12.68km Total length of pipe laid - 4.21km (kRK laid - 1.59km SEPC laid 2.62km ) Balance to be laid -8.47km Charged length- 2.50km Handed over to PH division- 2.50km | Kozhikode Proj AE 1 Urban | |
01 Jul 2020 | Eravathu kunnu North Zone Total length of pipe to be laid - 24.32km Total length of pipe laid - 0.87kmkm (kRK laid - 0.00km SEPC laid - 0.86km) Balance to be laid -23.46km Charged length -0.00km | Kozhikode Proj AE 1 Urban | |
01 Jul 2020 | Pottammal Zone Total length of pipe to be laid - 52.04km Total length of pipe laid - 38.70km (kRK laid - 8.15km ,SEPC laid - 30.55km) Balance to be laid- 13.34km Charged length- 24.00km Handed over to PH division - 24.00km | Kozhikode Proj AE 1 Urban | |
01 Jul 2020 | Balamandiram Zone Total length of pipe to be laid - 51.01km, Total length of pipe laid - 39.32km (kRK laid -12.20km , SEPC laid - 27.12km) Balance to be laid - 11.69km Charged length -16.10km Handed over to PH division -16.10km | Kozhikode Proj AE 1 Urban | |
01 Jul 2020 | Easthill Zone Total length of pipe to be laid - 60.07km Total length of pipe laid - 43.39km (kRK laid - 11.52km , SEPC laid- 31.87km) Balance to be laid - 16.68km Charged length - 14.82km Handed over to PH division- 14.82km | Kozhikode Proj AE 1 Urban |