Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2021 Final bill submitted to HO on 24.08.2021, As laid drawing submitted by contractor SPCL. But the same is returned for re-submitting after incorporating correction noted. Kozhikode Project Dn AE5
27 Jan 2021 Contract terminated at the risk and cost of contractor vide order no. KWA/JICA/KKD-2557-P3R1/2012, dated 03.09.2020. On termination, the physical progress achieved was 64.21%. Final bill submitted to CE(P&O) Kozhikode Proj AEE Urban
27 Nov 2020 JICA Closure bill under preparation Kozhikode Project Dn EE
13 Nov 2020 JICA Closure bill under preparation Kozhikode Project Dn EE
18 Aug 2020 Contract terminated vide order No KWA/JICA/CE/KKD/P3R1/749/2015 of CE(P&O) dated 17/06/2020. Kozhikode Proj AE 1 Urban
01 Jul 2020 Eravathukunnu south Zone- Total length of pipe to be laid - 12.68km Total length of pipe laid - 4.21km (kRK laid - 1.59km SEPC laid 2.62km ) Balance to be laid -8.47km Charged length- 2.50km Handed over to PH division- 2.50km Kozhikode Proj AE 1 Urban
01 Jul 2020 Eravathu kunnu North Zone Total length of pipe to be laid - 24.32km Total length of pipe laid - 0.87kmkm (kRK laid - 0.00km SEPC laid - 0.86km) Balance to be laid -23.46km Charged length -0.00km Kozhikode Proj AE 1 Urban
01 Jul 2020 Pottammal Zone Total length of pipe to be laid - 52.04km Total length of pipe laid - 38.70km (kRK laid - 8.15km ,SEPC laid - 30.55km) Balance to be laid- 13.34km Charged length- 24.00km Handed over to PH division - 24.00km Kozhikode Proj AE 1 Urban
01 Jul 2020 Balamandiram Zone Total length of pipe to be laid - 51.01km, Total length of pipe laid - 39.32km (kRK laid -12.20km , SEPC laid - 27.12km) Balance to be laid - 11.69km Charged length -16.10km Handed over to PH division -16.10km Kozhikode Proj AE 1 Urban
01 Jul 2020 Easthill Zone Total length of pipe to be laid - 60.07km Total length of pipe laid - 43.39km (kRK laid - 11.52km , SEPC laid- 31.87km) Balance to be laid - 16.68km Charged length - 14.82km Handed over to PH division- 14.82km Kozhikode Proj AE 1 Urban