Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jan 2024 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
01 Jan 2024 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
29 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
26 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
22 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
21 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
19 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
18 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
16 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
12 Dec 2023 716 FHTC & 74 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE