Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Mar 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
29 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
20 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
17 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
12 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
12 Feb 2024 | 22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2313 FHTC and 652 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . | Perinthalmanna AE | |
08 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
07 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
06 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
03 Feb 2024 | 758 FHTC &76 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE |