| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. | Mathilakam AE | |
| 08 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. | Mathilakam AE | |
| 07 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. | Irinjalakkuda PH Dn EE | |
| 07 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 05 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 03 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 02 Mar 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 28 Feb 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 26 Feb 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE | |
| 23 Feb 2022 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER under preparation. Package VI contractor filed a case. As per interim order, hearing conducted by SE and MD. | Mathilakam AE |