Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 May 2024 | Total pipe laid - 3.2761 Km.House connection shifting work on-going. | Palakkad Project Dn EE | |
22 May 2024 | Total pipe laid - 2.4701 Km.House connection shifting work on-going. | Palakkad Project Dn EE | |
20 May 2024 | Total pipe laid - 2.021 Km.House connection shifting work on-going. | Palakkad Project Dn EE | |
18 May 2024 | Total laid - 1.4261Km.Today main line laid- ▫️90mm PN 8 - 366m in kallamkuzhi - Rajeev colony Road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 839.8m Total laid - 1426.1m | Palakkad Proj AE 3 | |
15 May 2024 | Total laid - 956.1m.Today main line laid- ▫️90mm PN 8 - 180.8m in kallamkulam - kunnumpuram Road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 369.8m | Palakkad Proj AE 3 | |
13 May 2024 | Today main line laid- 110mm PN 8 - 19.85m in Kanjiram-Kallamkulam-Kolppadam road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 24m Total laid - 610.3m | Palakkad Proj AE 3 | |
10 May 2024 | Today main line laid- 110mm PN 8 - 19.85m in Kanjiram-Kallamkulam-Kolppadam road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 24m Total laid - 610.3m | Palakkad Proj AE 3 | |
06 May 2024 | Agreement executed by the the contractor on 14th March 2024 & Full pipe supplied 14km's for the work. | Palakkad Proj AE 3 | |
01 May 2024 | Agreement executed by the the contractor on 14th March 2024 & Full pipe supplied 14km's for the work. | Palakkad Proj AE 3 | |
16 Apr 2024 | Supply of pipe for the work. | Palakkad Proj AE 3 |