Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2024 | Total laid till now- 2.107kms. Today main line laid-323m in (Chullimunda, parakkal road). | Palakkad Proj AE 3 | |
02 May 2024 | Total laid till now- 1.539kms. Today main line laid-332m in (Vazhempuram , Arappara ) | Palakkad Proj AE 3 | |
01 May 2024 | Total laid till now- 1.207 kms .Today main line laid-120m in (Vazhempuram , Arappara ) | Palakkad Proj AE 3 | |
30 Apr 2024 | Today main line laid-250m in (Vazhempuram , Ayyappankavu ) 90mm HDPE PN 8-1.087 mts laied so far. | Palakkad Proj AE 3 | |
24 Apr 2024 | Today main line laid-150m in Vazhempuram 90mm HDPE PN 8-559 mts | Palakkad Proj AE 3 | |
23 Apr 2024 | Today main line laid-150m in Vazhempuram 90mm HDPE PN 8-362 mts | Palakkad Proj AE 3 | |
22 Apr 2024 | Today main line laid-150m in Vazhempuram 90mm HDPE PN 8-150ms | Palakkad Proj AE 3 | |
29 Feb 2024 | 90mm PN-8 PE-100 HDPE Pipe 825 mts supplied. | Palakkad Proj AE 3 | |
26 Feb 2024 | 90mm PN-8 PE-100 HDPE Pipe-ISI - 1475 mts supplied. | Palakkad Proj AE 3 | |
24 Feb 2024 | 90mm PN-8 PE-100 HDPE Pipe-ISI 2700 mts supplied. | Palakkad Proj AE 3 |