Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 May 2024 | GI pipe 100mm medium - 198 mts GI pipe 80mm medium - 1002 mts pipe supplied on 29/05/24. | Palakkad Proj AE 3 | |
25 May 2024 | 90mm PN-8 PE-100 HDPE Pipe-ISI 5000 mts & 110mm HDPE Pipe -1000mts supplied on 25/05/2024. | Palakkad Proj AE 3 | |
03 Jun 2024 | Total laid till now- 5.264kms. Today main line laid-150m ( ward-2 Vaduthalathottam) | Palakkad Proj AE 3 | |
01 Jun 2024 | Total laid till now- 5.114kms.Today main line laid-80m ( ward-2 Vaduthalathottam) | Palakkad Proj AE 3 | |
29 May 2024 | Total laid till now- 4.834kms.Today main line laid-144m ( ward-2 Vaduthalathottam) | Palakkad Proj AE 3 | |
27 May 2024 | Total laid till now- 4.590Kms. Today main line laid-210m ( ward-2 Vaduthalathottam) | Palakkad Proj AE 3 | |
22 May 2024 | Total laid till now- 3.810kms. Today main line laid-9m in Kottathamara & ward-4 mankurussi (Interconnection work of HDPE 90mm to existing PVC of 75mm) | Palakkad Proj AE 3 | |
20 May 2024 | Total laid till now- 3.801kms. Today main line laid-244m in (Arappara-Kottathamara road) | Palakkad Proj AE 3 | |
15 May 2024 | Total laid till now- 2.937kms .Today main line laid-175m in (Chullimunda) | Palakkad Proj AE 3 | |
13 May 2024 | Total laid till now- 2762m.Today main line laid-425m in (Mundampok) | Palakkad Proj AE 3 |