29 May 2024 GI pipe 100mm medium - 198 mts GI pipe 80mm medium - 1002 mts pipe supplied on 29/05/24. Palakkad Proj AE 3
25 May 2024 90mm PN-8 PE-100 HDPE Pipe-ISI 5000 mts & 110mm HDPE Pipe -1000mts supplied on 25/05/2024. Palakkad Proj AE 3
03 Jun 2024 Total laid till now- 5.264kms. Today main line laid-150m ( ward-2 Vaduthalathottam) Palakkad Proj AE 3
01 Jun 2024 Total laid till now- 5.114kms.Today main line laid-80m ( ward-2 Vaduthalathottam) Palakkad Proj AE 3
29 May 2024 Total laid till now- 4.834kms.Today main line laid-144m ( ward-2 Vaduthalathottam) Palakkad Proj AE 3
27 May 2024 Total laid till now- 4.590Kms. Today main line laid-210m ( ward-2 Vaduthalathottam) Palakkad Proj AE 3
22 May 2024 Total laid till now- 3.810kms. Today main line laid-9m in Kottathamara & ward-4 mankurussi (Interconnection work of HDPE 90mm to existing PVC of 75mm) Palakkad Proj AE 3
20 May 2024 Total laid till now- 3.801kms. Today main line laid-244m in (Arappara-Kottathamara road) Palakkad Proj AE 3
15 May 2024 Total laid till now- 2.937kms .Today main line laid-175m in (Chullimunda) Palakkad Proj AE 3
13 May 2024 Total laid till now- 2762m.Today main line laid-425m in (Mundampok) Palakkad Proj AE 3