Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | Balance work started .20 FHTCs out of 60 FHTCs completed | Thaliparamba WS Dn EE | |
28 Feb 2022 | 5313 FHTCs completed under JJM | Kalliassery W S Section - AE | |
04 Feb 2022 | 4704 FHTC s out of 5549 FHTC s completed | Kalliassery W S Section - AE | |
27 Jul 2021 | 3090/5549 | Thaliparamba WS Dn EE | |
19 Jul 2021 | 3090/5549 | Thaliparamba WS Dn EE | |
29 Jun 2021 | Work progress is effected due to water logging in the area. CC 6th and part bill submitted. | Thaliparamba WS Dn EE | |
12 Jun 2021 | 3080 FHTCs out of 5549 FHTCs completed (55%). | Thaliparamba WS Dn EE | |
01 Jun 2021 | 2935/5549 FHTCs completed | Thaliparamba WS Dn EE | |
16 Apr 2021 | 1959/5549 FHTCs compleyed | Thaliparamba WS Dn EE | |
09 Apr 2021 | 1756/5549 compleyed | Thaliparamba WS Dn EE |