Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Mar 2021 | 1643/5549 given | Thaliparamba WS Dn EE | |
12 Mar 2021 | 1218/5549 FHTCs provided | Thaliparamba WS Dn EE | |
05 Mar 2021 | 1168/5549 FHTCs provided | Thaliparamba WS Dn EE | |
17 Feb 2021 | 1168/5549 fhtc completed | Thaliparamba WS Dn EE | |
05 Feb 2021 | 1008/5549 FHTC given | Thaliparamba WS Dn EE | |
03 Feb 2021 | 963/5549 given | Thaliparamba WS Dn EE | |
26 Jan 2021 | 818/5549 FHTC GIVEN | Thaliparamba WS Dn EE | |
18 Dec 2020 | 246 FHTCs out of 5549 FHTCs completed (4%) | Thaliparamba WS Dn EE | |
16 Nov 2020 | 1 % completed | Thaliparamba WS Dn EE | |
13 Nov 2020 | Work Started | Thaliparamba WS Dn EE |