Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Dec 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024. Kanhangad Proj Dn AE - 2
28 Nov 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024. Kanhangad Proj Dn AE - 2
19 Nov 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024. Kanhangad Proj Dn AE - 2
13 Nov 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
07 Nov 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
04 Nov 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
29 Oct 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
25 Oct 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
22 Oct 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2
17 Oct 2024 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. Kanhangad Proj Dn AE - 2