Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
26 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
24 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
21 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
19 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
17 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
12 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
07 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
03 Jun 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 | |
31 May 2024 | 1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted.Time extension granted upto 31.03.2024 .Road cutting permission applied offline on 06/01/2024 to Plantation corporation which is under process.Time extension applied for 30.06.2024. | Kanhangad Proj Dn AE - 2 |