Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Nov 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
02 Nov 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
29 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
22 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
18 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
18 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
14 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
10 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
05 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
01 Oct 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 |