Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Dec 2024 | 103200 m pipe laid and 1183 HTC given,488 nos of FHTCs given | Koothuparamba Proj AE 2 | |
13 Dec 2024 | 103200 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
10 Dec 2024 | 150 mm DI-2200 m.100 mm DI-1250,90 mm pvc 8kg-4980.90 mm pvc10 kg- 5100,90 mm pvc 12.5kg-1896 mand 90 mm pvc 6kg- 1266 m pipes are supplied and 2221 m laid | Koothuparamba Proj AE 2 | |
10 Dec 2024 | 103200 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
05 Dec 2024 | 103200 m pipe laid and 1530HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
05 Dec 2024 | 103200 m pipe laid and 1600HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
28 Nov 2024 | 103200 m pipe laid and 1600HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
23 Nov 2024 | 103000 m pipe laid and 1600HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
19 Nov 2024 | 103000 m pipe laid and 1600HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 | |
14 Nov 2024 | 103000 m pipe laid and 1530 HTC given,417 nos of FHTCs given | Koothuparamba Proj AE 2 |