Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Jan 2023 | pipe line work in progress. 100 HTC given;14.60 kms of pipeline laid. Awaiting for PWD and road cutting permission which applied in ROW; Row/1037226/43142 | Kanhangad Proj Dn AE - 2 | |
05 Jan 2023 | pipe line work in progress , 100 HTC given. Awaiting for PWD and road cutting permission which applied in ROW; Row/1037226/43142 | Kanhangad Proj Dn AE - 2 | |
03 Jan 2023 | pipe line work in progress ,100 nos HTC given. | Kanhangad Proj Dn AE - 2 | |
29 Dec 2022 | pipe line work in progress ,72 nos HTC given. | Kanhangad Proj Dn AE - 2 | |
26 Dec 2022 | work in progress. | Kanhangad Proj Dn AE - 2 | |
22 Dec 2022 | Work in progress. | Kanhangad Proj Dn AE - 2 | |
19 Dec 2022 | Work in progress. | Kanhangad Proj Dn AE - 2 | |
15 Dec 2022 | Work in progress. | Kanhangad Proj Dn AE - 2 | |
12 Dec 2022 | Work in progress. | Kanhangad Proj Dn AE - 2 | |
08 Dec 2022 | Work in progress. | Kanhangad Proj Dn AE - 2 |