| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Feb 2024 | Excavation and PCC works for pump house completed. | Kollam WS Sn 2 - AE | |
| 13 Feb 2024 | Site handed over and work started | Kollam WS Sn 2 - AE | |
| 12 Feb 2024 | Site handover cannot done because no SHO proforma uploaded by the contractor. | Kollam WS Sn 2 - AE | |
| 06 Feb 2024 | Site handover cannot done because no SHO proforma uploaded by the contractor. | Kollam WS Sn 2 - AE | |