| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Apr 2024 | KSEB connection got on 27/3/24 and pump erection and interconnection works completed on 30/3/24 | Kollam WS Sn 2 - AE | |
| 25 Mar 2024 | KSEB connection not get till date, follow up action is ongoing, | Kollam WS Sn 2 - AE | |
| 21 Mar 2024 | KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted. | Kollam WS Sn 2 - AE | |
| 15 Mar 2024 | KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted. | Kollam WS Sn 2 - AE | |
| 11 Mar 2024 | KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted. | Kollam WS Sn 2 - AE | |
| 06 Mar 2024 | KSEB connection not get till date, follow up action is ongoing | Kollam WS Sn 2 - AE | |
| 01 Mar 2024 | KSEB connection not get till date, follow up action is ongoing | Kollam WS Sn 2 - AE | |
| 27 Feb 2024 | Pump house construction work completed. Pump set , and connected materials are received. Errection and commissioning Pending waiting for getting electricity connection from KSEB . | Kollam WS Sn 2 - AE | |
| 21 Feb 2024 | Pump house construction work completed. Pump set , and connected materials are received. Pending for getting electricity connection. | Kollam WS Sn 2 - AE | |
| 17 Feb 2024 | Pump house construction work in progress and pump set received. | Kollam WS Sn 2 - AE |