| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Oct 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 07 Oct 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 01 Oct 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 26 Sep 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 18 Sep 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 09 Sep 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 06 Sep 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 02 Sep 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 27 Aug 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE | |
| 23 Aug 2024 | Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted | Devikulam AE |