Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Nov 2024 111 nos of FHTCS Completed till date,Contractor given letter to short close the work Devikulam AE
11 Nov 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
08 Nov 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
05 Nov 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
02 Nov 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
01 Nov 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
30 Oct 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
29 Oct 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
28 Oct 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE
21 Oct 2024 Work is temporarily halted due to the unavailability of new FHTCs from existing lines. Part bill 5 submitted Devikulam AE