| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Mar 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 24 Feb 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 12 Feb 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 11 Feb 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 06 Feb 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 03 Feb 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 31 Jan 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 28 Jan 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 24 Jan 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE | |
| 21 Jan 2025 | 111 nos. of FHTCS Completed till date, Contractor given letter to short close the work | Devikulam AE |