| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2026 | 3rd brace concrete completed | Thalassery PH Sn AE | |
| 08 Jul 2026 | Column concrete on progress | Thalassery PH Sn AE | |
| 17 Jun 2026 | plinth beam concrete on progress | Thalassery PH Sn AE | |
| 04 Jun 2026 | steel work for plinth beam on progress | Thalassery PH Sn AE | |
| 29 Apr 2026 | Pedestal column concrete completed, back filling first stage on progress | Thalassery PH Sn AE | |
| 18 Apr 2026 | Pedestal column concrete completed, back filling first stage on progress | Thalassery PH Sn AE | |
| 10 Apr 2026 | Column concrete on progress | Thalassery PH Sn AE | |
| 30 Mar 2026 | PCC completed, centering work of footing on progress | Thalassery PH Sn AE | |
| 23 Mar 2026 | PCC on progress | Thalassery PH Sn AE | |
| 11 Mar 2026 | Work started | Thalassery PH Sn AE |