Status Date Overall Project Status Project Officer Contact
28 Sep 2026 3rd brace concrete completed Thalassery PH Sn AE
08 Jul 2026 Column concrete on progress Thalassery PH Sn AE
17 Jun 2026 plinth beam concrete on progress Thalassery PH Sn AE
04 Jun 2026 steel work for plinth beam on progress Thalassery PH Sn AE
29 Apr 2026 Pedestal column concrete completed, back filling first stage on progress Thalassery PH Sn AE
18 Apr 2026 Pedestal column concrete completed, back filling first stage on progress Thalassery PH Sn AE
10 Apr 2026 Column concrete on progress Thalassery PH Sn AE
30 Mar 2026 PCC completed, centering work of footing on progress Thalassery PH Sn AE
23 Mar 2026 PCC on progress Thalassery PH Sn AE
11 Mar 2026 Work started Thalassery PH Sn AE