Status Date Overall Project Status Project Officer Contact
03 Mar 2026 Work started site clearing, marking on progress Thalassery PH Sn AE
23 Feb 2026 Work started, site clearing and earth work excavation on progress Thalassery PH Sn AE
18 Feb 2026 Agreement executed Thalassery PH Sn AE
18 Feb 2026 work completed & final bill under preparation Thalassery PH Sn AE
09 Feb 2026 Agreement executed Thalassery PH Sn AE
29 Jan 2026 Agreement executed Thalassery PH Sn AE
29 Jan 2026 Agreement executed Thalassery PH Sn AE
19 Jan 2026 Agreement executed Thalassery PH Sn AE
08 Jan 2026 Agreement executed Thalassery PH Sn AE
05 Jan 2026 Agreement executed Thalassery PH Sn AE