| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Feb 2023 | Road restoration amount payment completed waiting for sanction letter from PWD. | Painavu PH Section AE | |
| 14 Feb 2023 | Road cutting permission procedures going on | Painavu PH Section AE | |
| 06 Feb 2023 | Road cutting permission procedures going on | Painavu PH Section AE | |
| 25 Jan 2023 | Road Cutting permission procedures going on | Painavu PH Section AE | |
| 20 Jan 2023 | Permission was granted to cut the road | Painavu PH Section AE | |
| 10 Jan 2023 | Pipe laying work is going on | Painavu PH Section AE | |
| 04 Jan 2023 | Pipe laying in progress | Painavu PH Section AE | |
| 26 Dec 2022 | Pipe Laying in Progress | Painavu PH Section AE | |
| 17 Dec 2022 | Pipe Laying Works in Progress | Painavu PH Section AE | |
| 13 Dec 2022 | Pipe Laying in Progress | Painavu PH Section AE |