| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2023 | CC Ist & Final Bill Submitted | Painavu PH Section AE | |
| 27 Apr 2023 | Work Completed on 17/04/2023 | Painavu PH Section AE | |
| 13 Apr 2023 | Road Crossing Work Completed on 13/04/2023 | Painavu PH Section AE | |
| 11 Apr 2023 | Contractor has arranged Road Crossing Work. Work is going on | Painavu PH Section AE | |
| 31 Mar 2023 | Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line | Painavu PH Section AE | |
| 28 Mar 2023 | Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line | Painavu PH Section AE | |
| 23 Mar 2023 | Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line | Painavu PH Section AE | |
| 10 Mar 2023 | Road restoration amount payment completed waiting for sanction letter from PWD. Road cutting agreement executed with PWD | Painavu PH Section AE | |
| 08 Mar 2023 | Road restoration amount payment completed waiting for sanction letter from PWD | Painavu PH Section AE | |
| 27 Feb 2023 | Road restoration amount payment completed waiting for sanction letter from PWD | Painavu PH Section AE |