24 Jun 2023 CC Ist & Final Bill Submitted Painavu PH Section AE
27 Apr 2023 Work Completed on 17/04/2023 Painavu PH Section AE
13 Apr 2023 Road Crossing Work Completed on 13/04/2023 Painavu PH Section AE
11 Apr 2023 Contractor has arranged Road Crossing Work. Work is going on Painavu PH Section AE
31 Mar 2023 Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line Painavu PH Section AE
28 Mar 2023 Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line Painavu PH Section AE
23 Mar 2023 Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line Painavu PH Section AE
10 Mar 2023 Road restoration amount payment completed waiting for sanction letter from PWD. Road cutting agreement executed with PWD Painavu PH Section AE
08 Mar 2023 Road restoration amount payment completed waiting for sanction letter from PWD Painavu PH Section AE
27 Feb 2023 Road restoration amount payment completed waiting for sanction letter from PWD Painavu PH Section AE