Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Nov 2023 | Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. | Kollam Project HD | |
15 Jun 2023 | One new package were added. Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. | Kollam Project HD | |
03 Apr 2023 | Out of 5 packages, 2 nos completed. Package 2 99% completed except NHAI crossing at Kalluvathukkal Jn which is scheduled to start on 05.04.2023. Packages 3 & 5 for construction and reformation of weirs are in progress. | Kollam Project Dn EE | |
11 Jun 2022 | NHAI deputy manager (Technical )visited Kalluvathukkal crossing point with KWA officials and NHAI Contractors representatives for ensuring Technical feasibility of crossing on 10.06.2022 | Kollam Project HD | |
26 May 2022 | NHAI representative assured to accord sanction for NH 66 crossing at Kalluvathukkal junction within one week in Road coordination committee held in the chamber of Hon District Collector Kollam on 26-05-22 | Kollam Project HD | |
16 Mar 2022 | Total 5 packages. Package I (95%)and Package II (95%) Work in progress. Package III- Works started, ring bund works in progress .package 4-Works completed and handed over to PH Division, Package 5- ring bund works started. | Kollam Project HD | |
13 Jan 2022 | Total 5 packages. Package I (89%)and Package II (89%) Work in progress. Package III- Works started, ring bund works in progress .package 4-Works completed and handed over to PH Division, Package 5- Tender finalized and selection notice issued. | Kollam Project HD | |
26 Oct 2021 | Total 5 packages. Package I (79%)and Package II (83%) Work in progress. Package 3-Agreement executed, Mobilization works started, ring bund works in progress .package 4-Works completed and handed over to PH Division, Package 5- Revised estimate received from Irrigation department and forwarded for TS | Kollam Project HD | |
07 Jul 2021 | Total 5 packages.Package I (53%)and Package II (44%) Work in progress.Package 3-Agreement executed,Mobilization works started , ring bund works in progress .package 4-Works completed and handed over to PH Division, Package 5-tendered but no bid received, Recasted estimate received from Irrigation department and forwarded for TS | Kollam Project HD | |
03 Jul 2021 | Total 5 packages.Package I (52%)and Package II (42%) Work in progress.Package 3-Agreement executed,Mobilization works started , ring bund works in progress .package 4-Works completed and handed over to PH Division, Package 5-tendered but no bid received, Recasted estimate received from Irrigation department and forwarded for TS | Kollam Project HD |