| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Mar 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE | |
| 26 Mar 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE | |
| 20 Mar 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE | |
| 14 Mar 2024 | Agreement to be executed. LoA issued on 04.03.2024 | Kollam PH Dn EE |