Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Mar 2024 Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing Kottiyam PH Sn AE
26 Mar 2024 Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing Kottiyam PH Sn AE
20 Mar 2024 Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing Kottiyam PH Sn AE
14 Mar 2024 Agreement to be executed. LoA issued on 04.03.2024 Kollam PH Dn EE