| 07 May 2024 | Pump control room, disinfectant stacking room and Bleaching powder tank fixing base purlin fixing ongoing | Kottiyam PH Sn AE | |
| 06 May 2024 | Pump control room, disinfectant stacking room and Bleaching powder tank fixing base side covering with corrugated sheet ongoing | Kottiyam PH Sn AE | |
| 04 May 2024 | Pump control room, disinfectant stacking room and Bleaching powder tank fixing base completed upto plinth level. | Kottiyam PH Sn AE | |
| 30 Apr 2024 | KSEB connection received and pump set errected | Kottiyam PH Sn AE | |
| 27 Apr 2024 | KSEB connection received and pump set errected | Kottiyam PH Sn AE | |
| 23 Apr 2024 | KSEB connection received and pump set errected | Kottiyam PH Sn AE | |
| 19 Apr 2024 | KSEB connection received and pump set errected | Kottiyam PH Sn AE | |
| 15 Apr 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE | |
| 09 Apr 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE | |
| 02 Apr 2024 | Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing | Kottiyam PH Sn AE |