Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Dec 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
07 Dec 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
02 Dec 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Perinthalmanna AE
28 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
20 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
13 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
07 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
06 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Perinthalmanna AE
03 Nov 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE
30 Oct 2023 Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. Mankada AE