Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-1015 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
21 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-995 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
18 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-995 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
15 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-985 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
13 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-975 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
11 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Perinthalmanna AE |
|
06 Mar 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
21 Feb 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
17 Feb 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|
14 Feb 2024 |
Package 1, 2, 3,4 completed, package 5 only on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-623 FHTCs completed. |
Mankada AE |
|