Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Aug 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-591 FHTCs completed. |
Mankada AE |
|
05 Aug 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-570 FHTCs completed. |
Mankada AE |
|
01 Aug 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-550 FHTCs completed. |
Mankada AE |
|
29 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-535 FHTCs completed. |
Mankada AE |
|
24 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-535 FHTCs completed. |
Mankada AE |
|
19 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-520 FHTCs completed. |
Mankada AE |
|
14 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-500 FHTCs completed. |
Mankada AE |
|
10 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-500 FHTCs completed. |
Mankada AE |
|
04 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-500 FHTCs completed. |
Mankada AE |
|
01 Jul 2023 |
Package 1, 2, 3 completed, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-847 FHTCs completed, Package 4-500 FHTCs completed. |
Perinthalmanna AE |
|