Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | Blue matching | Chowara AE | |
07 Feb 2024 | New Pump Set Installation work | Chowara AE | |
29 Jan 2024 | detached existing pump set and column pipe etc... | Chowara AE | |
27 Jan 2024 | detaching existing pump set | Chowara AE | |
25 Jan 2024 | Pump and motor delivered to site. Starter yet to be delivered. Erection of pump and motor is pending. | Chowara AE | |
22 Jan 2024 | Pump and motor delivered to site. Starter yet to be delivered. Erection of pump and motor is pending. | Angamaly AEE | |
17 Jan 2024 | VT Pump set Supplied at HW Section Chowara | Chowara AE | |
09 Jan 2024 | Work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
05 Jan 2024 | Work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
05 Jan 2024 | Work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE |