Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
21 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
19 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
15 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
13 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Chowara AE | |
11 Sep 2023 | work terminated at risk and cost of the contractor on 17.08.2023 | Aluva PH Dn EE | |
08 Sep 2023 | Agreement executed | Chowara AE | |
06 Sep 2023 | Agreement executed | Chowara AE | |
04 Sep 2023 | Agreement executed | Chowara AE | |
01 Sep 2023 | Agreement executed | Chowara AE |