- JJM-VADAKKEKARA PT in Ernakulam District...
JJM-VADAKKEKARA PT in Ernakulam District -Part I-Improvements of water treatment Plant-Supply and erection of 600 HP VT motor pump set in PWPH having discharge 2736 m3/Hour against a total head of 42 m in 63 MLD plant at Chowara -Part I
Project |
JJM-VADAKKEKARA PT in Ernakulam District -Part I-Improvements of water treatment Plant-Supply and erection of 600 HP VT motor pump set in PWPH having discharge 2736 m3/Hour against a total head of 42 m in 63 MLD plant at Chowara -Part I |
Project Code |
EKMJJM082012339 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-VADAKKEKARA PT in Ernakulam District -Part I-Improvements of water treatment Plant-Supply and erection of 600 HP VT motor pump set in PWPH having discharge 2736 m3/Hour against a total head of 42 m in 63 MLD plant at Chowara -Part I |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
48250000
|
AS Number |
G.O (Rt) No: 541/2020 |
TS Amount (Rs) |
9800000 |
TS Number |
TS/2022-2023/2022/3066 Dated: 29-07-2022 |
Total Bill Submitted (Rs) |
7556903 |
Total Bill Paid (Rs) |
|
Population Benefitted |
100000 |
Capacity in MLD |
63.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
VADAKKEKARA PT in Ernakulam District |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-VADAKKEKARA PT in Ernakulam District -Part I-Improvements of water treatment Plant-Supply and erection of 600 HP VT motor pump set in PWPH having discharge 2736 m3/Hour against a total head of 42 m in 63 MLD plant at Chowara -Part I |
Chowara HW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
work 90% completed |
Chowara AE |
|
18 Jun 2024 |
work 90% completed |
Chowara AE |
|
11 Jun 2024 |
work 80% completed |
Chowara AE |
|
07 Jun 2024 |
work 80% completed |
Chowara AE |
|
03 Jun 2024 |
work 80% completed |
Chowara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/08/2022 |
Scheduled date of Completion of the Project |
21 May 2023 |
Expected date of Completion |
21/05/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
29 Jul 2022 |