Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jul 2021 | Work in progress | 3% Completed | 19/07/2021 90mm pvc 6 kg-24996.00 m supplied at site and 7700m laid | Chittur Project Dn - AE 2 | |
11 Jul 2021 | Work in progress | 1% Completed | 11/07/2021 90mm pvc 6 kg-24996.00 m supplied at site and 5000.00m laid | Chittur Project Dn - AE 2 | |
03 Jul 2021 | Work in progress | 1% Completed | 03/07/2021 90mm pvc 6kg-1392 m laid | Chittur Project Dn - AE 2 | |
28 Jun 2021 | Work in progress | 1% Completed | 28/06/2021 90mm pvc 6kg-475m laid | Chittur Project Dn - AE 2 | |
20 Jun 2021 | Agreement executed on 31.05.2021 | Chittur Project Dn - AE 2 | |
17 Jun 2021 | Agreement executed on 31.05.2021 | Chittur Project Dn - AE 2 | |
08 Jun 2021 | site inspection conducted AE,AEE, with contractor | Chittur Project Dn - AE 2 | |
01 Jun 2021 | work order issued on 12.05.2021 to Sri.David Mangan ,Mangan house,Arattupuzha ,. | Chittur Project Dn - AE 2 | |
27 May 2021 | work order issued on 12.05.2021 to Sri.David Mangan ,Mangan house,Arattupuzha ,. | Chittur Project Dn - AE 2 | |
19 May 2021 | work order issued on 12.05.2021 to Sri.David Mangan ,Mangan house,Arattupuzha ,Thrissur | Chittur Project Dn - AE 2 |