05 Sep 2021 Work in progress | 25% Completed | 05/09/2021 90mm pvc 6 kg-24996.00 m supplied at site and 22.437km laid Chittur Project Dn - AE 2
31 Aug 2021 Work in progress | 22% Completed | 31/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 20.191km laid Chittur Project Dn - AE 2
29 Aug 2021 Work in progress | 5% Completed | 29/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 20.191km laid Chittur Project Dn - AE 2
28 Aug 2021 Work in progress | 5% Completed | 28/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 20.191km laid Chittur Project Dn - AE 2
16 Aug 2021 Work in progress | 5% Completed | 16/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 19.191km laid Chittur Project Dn - AE 2
12 Aug 2021 Work in progress | 3% Completed | 12/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 15.50 km laid Chittur Project Dn - AE 2
09 Aug 2021 Work in progress | 3% Completed | 09/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 14500.00m laid Chittur Project Dn - AE 2
01 Aug 2021 Work in progress | 3% Completed | 01/08/2021 90mm pvc 6 kg-24996.00 m supplied at site and 11300.00m laid Chittur Project Dn - AE 2
27 Jul 2021 Work in progress | 3% Completed | 27/07/2021 90mm pvc 6 kg-24996.00 m supplied at site and 10300.00m laid Chittur Project Dn - AE 2
24 Jul 2021 Work in progress | 3% Completed | 24/07/2021 90mm pvc 6 kg-24996.00 m supplied at site and 8500m laid Chittur Project Dn - AE 2