Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Jun 2024 | PVC Laying details Today layed length 90 mm 8 kg = 108 M Total layed length =3350 M GI laying details 80 mm GI = nil Total layed length= 768 M | Palakkad Proj Dn AE 4 | |
15 Jun 2024 | PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 27 M Total layed length= 652 M | Palakkad Proj Dn AE 4 | |
08 Apr 2024 | PVC Laying details Today laid length 90 mm 8 kg = 84 M Total layed length = 210 M GI Work has not started yet | Palakkad Proj Dn AE 4 | |
05 Apr 2024 | PVC Laying details Cumulative length = 0 Today laid length 90 mm 8 kg = 24 M GI Work has not started yet | Palakkad Proj Dn AE 4 | |
01 Apr 2024 | Pipe supplied.90mm 8kg PVC 15000m completed. | Palakkad Proj Dn AE 4 | |
03 Mar 2024 | Site hand overed to contractor. | Palakkad Proj Dn AE 4 | |
22 Feb 2024 | Agreement executed on this date - 41/2023-24/SE/PHC/PKD | Palakkad Proj Dn AE 4 | |
19 Jan 2024 | Work order issued. KWA/PHC/PKD/JJM/Ambalapara/2023-24 | Palakkad Proj Dn AE 4 | |
22 Feb 2024 | Agreement executed on this date. Agreement no: 41/2023-24/SE/PHC/PKD | Palakkad Proj Dn AE 4 |