Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Oct 2021 | 82 nos fhtc given | Attingal WS Dn EE | |
26 Oct 2021 | 82 nos fhtc given | Attingal WS Dn EE | |
25 Oct 2021 | 61 nos fhtc given | Attingal WS Dn EE | |
24 Oct 2021 | 61 nos fhtc given | Attingal WS Dn EE | |
23 Oct 2021 | 61 nos fhtc given | Attingal WS Dn EE | |
22 Oct 2021 | 46 nos fhtc given | Attingal WS Dn EE | |
21 Oct 2021 | 34 nos fhtc given | Attingal WS Dn EE | |
20 Oct 2021 | 14 nos fhtc given | Attingal WS Dn EE | |
19 Oct 2021 | work started | Attingal WS Dn EE | |
18 Oct 2021 | work started | Attingal WS Dn EE |