Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Dec 2021 | 779 nos fhtc given | Attingal WS Dn EE | |
12 Dec 2021 | 779 nos fhtc given | Attingal WS Dn EE | |
06 Dec 2021 | 757 nos fhtc given | Attingal WS Dn EE | |
05 Dec 2021 | 729 nos fhtc given | Attingal WS Dn EE | |
03 Dec 2021 | 666 nos fhtc given | Attingal WS Dn EE | |
01 Dec 2021 | 651 nos fhtc given | Attingal WS Dn EE | |
30 Nov 2021 | 610 nos fhtc given | Attingal WS Dn EE | |
26 Nov 2021 | 559 nos fhtc given | Attingal WS Dn EE | |
25 Nov 2021 | No work due to heavy rain | Attingal WS Dn EE | |
24 Nov 2021 | 559 nos fhtc given | Attingal WS Dn EE |