Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jun 2024 | Work in progress. | Ollur AE | |
13 Jun 2024 | Work in progress. | Ollur AE | |
27 May 2024 | Work in progress. | Ollur AE | |
14 May 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,No of Connection-166 nos.Geo Tagged-161nos | Ollur AE | |
22 Apr 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,No of Connection-166 nos.Geo Tagged-161nos | Ollur AE | |
15 Apr 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,No of Connection-166 nos.Geo Tagged-161nos | Ollur AE | |
20 Mar 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,No of Connection-166 nos.Geo Tagged-161nos | Ollur AE | |
13 Mar 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,No of Connection-166 nos.Geo Tagged-161nos | Ollur AE | |
30 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-160nos.Geo Tagged-82nos | Ollur AE | |
25 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-160nos.Geo Tagged-82nos | Ollur AE |