Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-160nos.Geo Tagged-82nos | Ollur AE | |
15 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-160nos.Geo Tagged-82nos | Ollur AE | |
08 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-100nos. | Ollur AE | |
02 Jan 2024 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-100nos. | Ollur AE | |
28 Dec 2023 | Work in progress | Ollur AE | |
20 Dec 2023 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-100nos. | Ollur AE | |
15 Dec 2023 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-40nos. | Ollur AE | |
10 Dec 2023 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-40nos | Ollur AE | |
05 Dec 2023 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-40nos | Ollur AE | |
30 Nov 2023 | Work in progress. Total pipe laying -27500m,Submitt CC 1st & Part Bill ,no of Connection-20nos | Ollur AE |