Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Jul 2021 1395 out of 2404fhtc completed. Thaliparamba WS Dn EE
11 Jul 2021 1390 out of 2404 FHTC completed Thaliparamba WS Dn EE
08 Jul 2021 1375 out of 2404 FHTC completed. Thaliparamba WS Dn EE
29 Jun 2021 1358 out of 2404 completed Thaliparamba WS Dn EE
13 Jun 2021 1350 out of 2404 FHTCs completed Thaliparamba WS Dn EE
31 May 2021 1325 out of 2404FHTC completed Thaliparamba WS Dn EE
31 May 2021 1350 FHTC out of 2404 completed Thaliparamba WS Dn EE
06 May 2021 1172/2404 FHTC Provided Thaliparamba WS Dn EE
16 Apr 2021 962/2402 fhtc completed Thaliparamba WS Dn EE
16 Apr 2021 796/2402 fhtc completed Thaliparamba WS Dn EE