Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | Balance work started .10 FHTCs provided out of 200 | Thaliparamba WS Dn EE | |
17 Jun 2023 | Declared Har Ghar Jal | Thaliparamba WS Dn EE | |
22 Oct 2022 | 2404 out of 2404 completed | Pilathara WS Sn - AE | |
07 Apr 2022 | 1820 FHTC completed. | Thaliparamba WS Dn EE | |
03 Feb 2022 | 1730 FHTC completed.8695m pipes laid.Due to poor response of contractor Superintending Engineer arranged a meeting of contractor and Panchayath President on 03.02.2022. | Thaliparamba WS Dn EE | |
19 Nov 2021 | 1724 out of 2404 FHTC completed. | Thaliparamba WS Dn EE | |
08 Nov 2021 | 1680 out of 2404 FHTC completed. | Thaliparamba WS Dn EE | |
02 Oct 2021 | 1645 out of 2404 FHTC completed. | Thaliparamba WS Dn EE | |
15 Sep 2021 | 1592 out of 2404 FHTC completed | Thaliparamba WS Dn EE | |
20 Jul 2021 | 1410 out of 2404 FHTC completed. | Thaliparamba WS Dn EE |