Status Date Overall Project Status Project Officer Contact
14 Feb 2024 Balance work started .10 FHTCs provided out of 200 Thaliparamba WS Dn EE
17 Jun 2023 Declared Har Ghar Jal Thaliparamba WS Dn EE
22 Oct 2022 2404 out of 2404 completed Pilathara WS Sn - AE
07 Apr 2022 1820 FHTC completed. Thaliparamba WS Dn EE
03 Feb 2022 1730 FHTC completed.8695m pipes laid.Due to poor response of contractor Superintending Engineer arranged a meeting of contractor and Panchayath President on 03.02.2022. Thaliparamba WS Dn EE
19 Nov 2021 1724 out of 2404 FHTC completed. Thaliparamba WS Dn EE
08 Nov 2021 1680 out of 2404 FHTC completed. Thaliparamba WS Dn EE
02 Oct 2021 1645 out of 2404 FHTC completed. Thaliparamba WS Dn EE
15 Sep 2021 1592 out of 2404 FHTC completed Thaliparamba WS Dn EE
20 Jul 2021 1410 out of 2404 FHTC completed. Thaliparamba WS Dn EE