Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Oct 2023 | Work in progress | 1% Completed | 12/10/2023 PVC,GI, Pipes supplied at site and 110 mm pvc pipe laying work started pipe laid for a length of 408m /7.90km | Chittur Project Dn - AE 3 | |
12 Oct 2023 | Work in progress | 56% Completed | 12/10/2023 FHTC- 2334 Nos provided/out of 6055 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m 3) FHTC-1565NO/6055 no | Chittur Project Dn - AE 3 | |
07 Sep 2023 | Work in progress | 55% Completed | 07/09/2023 TOTAL PIPE LAID 5.082km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2082 m 3) FHTC-1565NO/6055 no | Chittur Project Dn - AE 3 | |
26 Aug 2023 | Work in progress | 45% Completed | 26/08/2023 TOTAL PIPE LAID 4.296km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 1296 m 3) FHTC-1530NO/6055 no | Chittur Project Dn - AE 3 | |
15 Aug 2023 | Work in progress | 40% Completed | 15/08/2023 TOTAL PIPE LAID 3.798km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe-798m 3) FHTC-799NO/6055 no | Chittur Project Dn - AE 3 | |
04 Aug 2023 | Work in progress | 32% Completed | 04/08/2023 TOTAL PIPE LAID 3.432km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe-432m 3) FHTC-600NO/6055 no | Chittur Project Dn - AE 3 | |
20 Jul 2023 | Work in progress | 30% Completed | 20/07/2023 TOTAL PIPE LAIDpipe-3.00km laid/8km FHTC-398 NO | Chittur Project Dn - AE 3 | |
13 Jul 2023 | Work in progress | 30% Completed | 13/07/2023 90mm pvc pipe-3.00km laid/8km | Chittur Project Dn - AE 3 | |
06 Jul 2023 | Work in progress | 1% Completed | 06/07/2023 Agreement executed on 31.03.2023 | Chittur Project Dn - AE 3 |