Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2024 | Work in progress | 60% Completed | 27/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
20 Jun 2024 | Work in progress | 60% Completed | 20/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
12 Jun 2024 | Work in progress | 60% Completed | 12/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
06 Jun 2024 | Work in progress | 60% Completed | 06/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
23 May 2024 | Work in progress | 60% Completed | 23/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
16 May 2024 | Work in progress | 60% Completed | 16/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
09 May 2024 | Work in progress | 60% Completed | 09/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
02 May 2024 | Work in progress | 60% Completed | 02/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
25 Apr 2024 | Work in progress | 60% Completed | 25/04/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 | Chittur Project Dn - AE 3 | |
19 Apr 2024 | Work in progress | 60% Completed | 19/04/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 605 | Chittur Project Dn - AE 3 |