Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2024 Work in progress | 60% Completed | 27/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 Chittur Project Dn - AE 3
20 Jun 2024 Work in progress | 60% Completed | 20/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 Chittur Project Dn - AE 3
12 Jun 2024 Work in progress | 60% Completed | 12/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055 Chittur Project Dn - AE 3
06 Jun 2024 Work in progress | 60% Completed | 06/06/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
23 May 2024 Work in progress | 60% Completed | 23/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
16 May 2024 Work in progress | 60% Completed | 16/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
09 May 2024 Work in progress | 60% Completed | 09/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
02 May 2024 Work in progress | 60% Completed | 02/05/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
25 Apr 2024 Work in progress | 60% Completed | 25/04/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 6055 Chittur Project Dn - AE 3
19 Apr 2024 Work in progress | 60% Completed | 19/04/2024 TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 2916 Nos provided/out of 605 Chittur Project Dn - AE 3