01 Jul 2024 Pkg 1-Work Ongoing. 25 Nos. Tagged. Bill submitted., Pkg 2-5300m 160mm PVC pipe laid out of 6600m . Road restoration work to be arranged. second and part bill under scrutiny in division. Pkg 3-Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation-90%, Pkg 4-Work has been completed-100% Thrissur PH Dn EE
28 Jun 2024 Pkg 1-Work Ongoing. 25 Nos. Tagged. Bill submitted., Pkg 2-5300m 160mm PVC pipe laid out of 6600m . Road restoration work to be arranged. second and part bill under scrutiny in division. Pkg 3-Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation-90%, Pkg 4-Work has been completed-100% Thrissur PH Dn EE
24 Jun 2024 Work Ongoing. Guruvayur PH Sn AE
22 Jun 2024 Work Ongoing. Thrissur PH Dn EE
21 Jun 2024 Work Ongoing. Thrissur PH Dn EE
20 Jun 2024 Work Ongoing. Thrissur PH Dn EE
19 Jun 2024 Work Ongoing. Guruvayur PH Sn AE
15 Jun 2024 Work Ongoing. Guruvayur PH Sn AE
14 Jun 2024 Work Ongoing. Guruvayur PH Sn AE
12 Jun 2024 Work Ongoing. Thrissur PH Dn EE