Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2024 | work ongoing and GSB Filling started | Guruvayur PH Sn AE | |
30 Jan 2024 | work ongoing and GSB Filling started | Guruvayur PH Sn AE | |
29 Jan 2024 | Pipe laying work - 5300 m Balance work ongoing and GSB Filling started | Guruvayur PH Sn AE | |
27 Jan 2024 | Pipe laying work - 5300 m Balance work ongoing and GSB Filling started | Guruvayur PH Sn AE | |
24 Jan 2024 | Pipe laying work - 5300 m Balance work ongoing and GSB Filling started | Guruvayur PH Sn AE | |
20 Jan 2024 | Pipe laying work - 5300 m Balance work ongoing. | Guruvayur PH Sn AE | |
18 Jan 2024 | Pipe laying work - 5300 m Balance work ongoing. | Guruvayur PH Sn AE | |
17 Jan 2024 | Pipe laying work - 5200 m Balance work ongoing. | Guruvayur PH Sn AE | |
16 Jan 2024 | Pipe laying work - 4100 m Balance work ongoing. | Guruvayur PH Sn AE | |
15 Jan 2024 | Pipe laying work - 4100 m Balance work ongoing. | Guruvayur PH Sn AE |