Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Feb 2024 work ongoing and GSB Filling started Guruvayur PH Sn AE
30 Jan 2024 work ongoing and GSB Filling started Guruvayur PH Sn AE
29 Jan 2024 Pipe laying work - 5300 m Balance work ongoing and GSB Filling started Guruvayur PH Sn AE
27 Jan 2024 Pipe laying work - 5300 m Balance work ongoing and GSB Filling started Guruvayur PH Sn AE
24 Jan 2024 Pipe laying work - 5300 m Balance work ongoing and GSB Filling started Guruvayur PH Sn AE
20 Jan 2024 Pipe laying work - 5300 m Balance work ongoing. Guruvayur PH Sn AE
18 Jan 2024 Pipe laying work - 5300 m Balance work ongoing. Guruvayur PH Sn AE
17 Jan 2024 Pipe laying work - 5200 m Balance work ongoing. Guruvayur PH Sn AE
16 Jan 2024 Pipe laying work - 4100 m Balance work ongoing. Guruvayur PH Sn AE
15 Jan 2024 Pipe laying work - 4100 m Balance work ongoing. Guruvayur PH Sn AE