| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Aug 2023 | Work Completed. Bill Sumitted | Kottarakkara PH Dn EE | |
| 04 Aug 2023 | 90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed | Valakom PH Sn AE | |
| 04 Aug 2023 | 90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed. | Valakom PH Sn AE | |
| 01 Aug 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 29 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 27 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 25 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 22 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 19 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 15 Jul 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE |