| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Apr 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 17 Apr 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 13 Apr 2023 | 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 11 Apr 2023 | 10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 09 Apr 2023 | 10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 05 Apr 2023 | 10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 03 Apr 2023 | 10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 30 Mar 2023 | 9km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress | Valakom PH Sn AE | |
| 27 Mar 2023 | work in progress | Valakom PH Sn AE | |
| 23 Mar 2023 | work in progress | Valakom PH Sn AE |